Projects

The MXSuite Projects module helps you to get a grip on your projects like dry dockings and refits.

Projects Basic vs Standard

There are two versions of the Projects module: Basic and Standard.
The Basic version is part of the Assets Tasks. The Standard version has more extensive functionality.


Projects Basic Projects Standard
Name the projects yes yes
Project start date and end date  yes yes
Project type yes yes
Project manager no yes
Project status and percentage completed no yes
Link Assets Tasks to Projects yes yes
Financial project overview  no yes
Link product orders to Projects no yes
Link service orders to Projects no yes
Create project reports no yes
Assign yard services with pricing no yes
Save project documents no yes
Save project photo's no yes

How do I create a new project?

  1. Open the Projects module in the left module bar
  2. Click on New... 
  3. Fill in all details for the new project
    projects-details.png

  4. Click on Save & close

 

How do I create a new project task?

  1. Open the module Assets Tasks
  2. Click on New task...
    projects-createprojecttask.png

  3. Describe the task in the Task name and in the tab Task description
  4. Eventually, link the task to a project type
  5. Click on Save & close

A task can be linked to a project type. When a project is created with that type, all tasks linked to that type will be linked to the newly created project.

Project types can be created and modified in Administration > Projects. The default project types are Standard, Intermediate and Special.

 

How do I assign a task to a project?

There are 2 options to link a task to a project. Assume that the task and the project have already been created.

Option 1
  1. Open the module Assets Tasks
  2. Right click at a project task
  3. Click on Link to project...
    project-linktasktoproject.png

  4. Select the project to which the task should be linked.
    project-linktasktoproject2.png

  5. Click on Save & close

 

Option 2
  1. Open the project to which the task should be linked.
  2. Open tab Tasks
  3. Click on New...
  4. All available project tasks are shown now
    projects-allprojecttasks.png

  5. Select the task(s) and click Save & close

How to register the progress of a project task?

  1. Open the tab Tasks in the project
  2. Open the task
  3. In the tab General, the estimated cost, contractor, and percentage (%) completed can be edited
    projects-taskcompleted-general.png

  4. Extra remarks, documents, and photos about the progress can be added in the related tabs.

If the task is completed, move the slider in the tab General to 100%.

How do I complete a project task?

  1. Open the task
  2. Move the slider to 100%
    projects-taskslider.png

  3. Click on Save & close